The Broadway Project

12 February, 2025

136 m3

waste diverted from landfill

90 t CO2

carbon saving

4,487

trees needed to absorb the equivalent greenhouse gas

The Broadway Project – Multiplex

LOCATION
The Broadway project was a large-scale development located in the heart of Westminster, London. The project covered a significant floor space, with a high-end residential and commercial mix contributing to the transformation of this prestigious area.

BACKGROUND TO THE PROJECT
The Broadway is a landmark mixed-use development that comprises six residential towers with luxury apartments, retail spaces, and office areas. This prestigious project, undertaken by Multiplex, required extensive protection solutions to maintain the quality and integrity of installed materials throughout the build process. Having worked with Multiplex on previous projects, Protec was trusted to deliver high-performance temporary protection solutions.

THE CHALLENGE
Given the high specification of finishes throughout The Broadway project, it was essential to ensure surfaces were protected against damage from heavy site traffic, equipment movement, and ongoing construction work. The protection needed to remain in place for an extended period to cover various phases of the build.

Specific challenges included:

  • Protecting high-value materials from impact damage, dust, and spills
  • Ensuring protection remained durable despite high footfall and mechanical access
  • Managing waste and sustainability commitments through responsible recycling

PROJECT SOLUTION
Protec was involved early in the project, working closely with Multiplex and their subcontractors to develop a tailored protection strategy. Based on site requirements, Proplex HD protection boards were recommended for their durability, impact resistance, and ability to withstand high-traffic conditions. These also comply with JCoP standards for fire risk management.

To support the project team, Protec provided guidance on the best application methods and regular site visits to ensure proper use of materials. The scale of this project required a significant volume of protection materials, delivered in phases to align with the construction schedule.

THE OUTCOME
The Broadway project was successfully completed with all protected surfaces remaining in excellent condition throughout the build. In alignment with sustainability goals, Protec collaborated with Multiplex and site logistics provider Madigan Gill to recover the used Proplex at the project’s conclusion. We recycled an impressive 25.64 tonnes of used Proplex temporary protection sheets that would have otherwise gone to landfill or incineration.

The recovered Proplex was processed through our recycling facility, where it was shredded, washed, and remanufactured into our industry-leading ProplexRE Sheets. These sheets are now in use on new construction sites, continuing the cycle of sustainability.

Share